            Enhanced Conceptual Design Report for 
                                   Woodward Avenue Water Treatment Plant

 Woodward Avenue WWTP Enhanced Conceptual Design Report


 Appendices:

 Appendix A - Existing Certificate of Approval
 Appendix B - Mass Balance
 Appendix C - Detailed Calculation of Raw Wastewater Pumping Station Rise Rate
 Appendix D - Raw Wastewater Pumping Station Construction Sequencing
 Appendix E - Philips Engineering Red Hill Creek Modifications Report
 Appendix F - CRA Electrical Report
List of Figures
 Figure 1 - WWTP & WTP Existing Distribution System Layout
 Figure 2 - Woodward Avenue Treatment Facility Site Plan
List of Tables
 Table 1 - Electrical Distribution System Conceptual Cost Estimate
List of Appendices
 Appendix A - Summary of WWTP and WTP Load Data
 Table A1 - Woodward Aggregated Future Electrical Load Calculations
 Table A2 - Woodward WWTP Future Electrical Load Calculations
 Table A3 - Woodward WTP Future Electrical Load Calculations
 Appendix B - Horizon Utilities Corporation System Information
 Appendix C - Concept Design Drawings
 Appendix D - Electrical Distribution System Conceptual Implementation Schedule
 Appendix E - Technical Memorandum No 1 - Fundamental Distribution Concepts
 Appendix F - Technical Memorandum No 2 - Distribution Design Options
 Appendix G - Excerpt From "Woodward Avenue Facilities - Energy Plant Development Plan"
 Appendix G - Detailed Cost Tables

 Drawings:

 C-001 - EXISTING SITE PLAN
 C-002 - PROPOSED SITE PLAN
 C-003 - OVERALL PROCESS FLOW DIAGRAM FOR UPGRADE AND EXPANSION
 C-004 - HYDRAULIC PROFILE EXISTING CONVENTIONAL ACTIVATED SLUDGE TRAIN
 C-005 - HYDRAULIC PROFILE MICRO SCREEN AND MEMBRANE FILTER TRAIN
 C-006 - HYDRAULIC PROFILE MICRO SCREEN AND MEMBRANE BIOREACTOR TRAIN
 C-007 - RAW WASTEWATER PUMPING STATION YARD PIPING LAYOUT
 C-008 - RAW WASTEWATER PUMPING STATION WET WELL PLAN
 C-009 - RAW WASTEWATER PUMPING STATION MAIN FLOOR PLAN
 C-010 - RAW WASTEWATER PUMPING STATION SECTION
 C-011 - RAW WASTEWATER PUMPING STATION STAGING PLAN - PHASE 1
 C-012 - RAW WASTEWATER PUMPING STATION STAGING PLAN - PHASE 2
 C-013 - RAW WASTEWATER PUMPING STATION STAGING PLAN - PHASE 3
 C-014 - RAW WASTEWATER PUMPING STATION STAGING PLAN - PHASE 4
 C-015 - PROCESS FLOW DIAGRAM CAS/MF (OPTION 1)
 C-016 - PROCESS FLOW DIAGRAM TMBR (OPTION 2)
 C-017 - SOUTH PLANT AERATION TANKS MODIFICATION AND RAS FLOWMETER PLAN
 C-018 - SOUTH PLANT SECONDARY CLARIFIER MODIFICATION PLAN
 C-019 - NORTH PLANT AERATION TANKS MODIFICATION PLAN
 C-020 - NORTH PLANT AERATION TANKS MODIFICATION SECTIONS
 C-021 - NORTH PLANT SECONDARY CLARIFIER MODIFICATION PLAN
 C-022 - PROPOSED SECONDARY TREATMENT AND MEMBRANE PLANT SITE PLAN
 C-023 - MICRO SCREEN FACILITY PLAN
 C-024 - AERATION TANKS, MEMBRANE FACILITIES & CHLORINE CONTACT CHAMBER PLAN
 C-025 - MEMBRANE BIOREACTOR PLAN
 C-026 - MEMBRANE BIOREACTOR SECTION
 C-027 - MEMBRANE FACILITY BLOWER BUILDING PLAN & SECTION
 C-028 - WAS THICKENING BUILDING PLAN FOR GRAVITY BELT THICKENER
 C-029 - DEWATERING BUILDING CENTRIFUGE PLAN AT EL. 87.00m
 C-030 - DEWATERING BUILDING BASEMENT PLAN AT EL. 79.325m
 C-031 - BIRCH AVENUE CSO PUMPING STATION SITE PLAN
 C-032 - PROPOSED CSO PUMPING STATION SITE PLAN: MAIN-KING CSO TANK SITE
 C-033 - PROPOSED BIRCH AVE, CSO PUMPING STATION MAIN FLOOR PLAN
 C-034 - PROPOSED BIRCH AVE, CSO PUMPING STATION PIPING PLAN AND SECTION
 C-035 - PRELIMINARY CONSTRUCTION CONTRACT LAYDOWN AREAS