|
|
City of Hamilton
Recreation Facility Renewal Program
The City of Hamilton in cooperation with the federal and provincial governments are pleased to receive infrastructure funding to improve several city-operated recreation centres, pools and arenas over the next year which will improve services for residents. Our goal is to maintain service with the least possible disruption to the public.
The table below presents facilities that may be closed for a period of time. Recreation programs may be moved to other locations to accommodate user activities. Updates on program location changes will be provided.
2011 Pool Maintenance Schedule
|
Facility |
Close |
Re-open |
| Ancaster Aquatic Centre |
June 22, 2011 |
June 28, 2011 |
| Ancaster Rotary Centre |
August 29, 2011 |
September 4, 2011 |
| Bennetto Recreation Centre |
August 29, 2011 |
September 11, 2011 |
| HG Brewster Pool |
September 5, 2011 |
September 11, 2011 |
| Central Memorial Recreation Centre |
December 19, 2011 |
December 23, 2011 |
| Dalewood Recreation Centre |
June 20, 2011 |
June 26, 2011 |
| Dundas Community Centre |
December 19, 2011 |
December 23, 2011 |
| Dundas Pool |
August 29, 2011 |
September 18, 2011 |
| Hill Park Recreation Centre |
June 14, 2011 |
June 26, 2011 |
| Huntington Park Recreation Centre |
August 29, 2011 |
September 11, 2011 |
| Jimmy Thompson Pool |
June 22, 2011 |
June 26, 2011 |
| Norman Pinky Lewis Recreation Centre |
June 15, 2011 |
June 26, 2011 |
| Riverdale Recreation Centre |
June 20, 2011 |
June 26, 2011 |
| Ryerson Recreation Centre |
September 12, 2011 |
September 25, 2011 |
| Sackville Hill Seniors Centre |
September 5, 2011 |
September 11, 2011 |
| Sir Wilfrid Laurier Recreation Centre |
December 12, 2011 |
December 18, 2011 |
| Sir Winston Churchill Recreation Centre |
September 5, 2011 |
September 11, 2011 |
| Valley Park Recreation Centre |
September 12, 2011 |
September 25, 2011 |
Major Renovations
|
Facility |
Renovation Work to be Completed |
Close |
Re-open |
Expanded Programs |
|
Sir Allan MacNab Recreation Centre |
- Replace the pool filtration system, HVAC and dehumidification systems
- Install air-conditioning for centre
- Interior upgrades to the pool ceiling
- Renovate change rooms and program space
- Upgrade out dated mechanical and electrical systems
- Install energy efficient and environmentally friendly systems and fixtures
|
March 31, 2010 |
Summer 2011 |
Ancaster Aquatic Centre
Hill Park Recreation Centre
Ryerson Recreation Centre |
|
Sir Wilfrid Laurier Recreation Centre |
- Replace HVAC and dehumidification system
- Install air conditioning for community rooms and administration area
- Repair exterior walk
- Remove acoustic ceiling and install new lighting and acoustic panels in the pool area
|
March 20, 2010 |
Fall 2010 |
|
|
Carlisle Arena |
- Refurbish interior finished and fixtures
- Upgrade mechanical and electrical systems
- Replace equipment to meet legislated requirement issues
- Replace pipes, arena floor, dasher boards, electrical and compressor
|
March 31, 2010 |
Fall 2010 |
|
|
Chedoke Twin Pad Arena |
- Refurbish interior finishes and fixtures
- Upgrade mechanical and electrical systems
- Replace equipment to meet legislated requirement issues
- Replace pipes, arena floor, dasher boards, electrical and compressor
|
April 4, 2010 |
Fall 2010 |
|
|
Inch Park Arena |
- Refurbish interior finishes and fixtures
- Upgrade mechanical and electrical systems
- Replace equipment to meet legislated requirement issues
- Replace pipes, arena floor, dasher boards, electrical and compressor
|
April 4, 2010 |
Winter 2011 |
|
|
Rosedale Arena |
- Refurbish interior finishes and fixtures
- Upgrade mechanical and electrical systems.
- Replace equipment to meet legislated requirement issues
- Replace pipes, arena floor, dasher boards, electrical and compressor
- Improve barrier free accessibility
|
April 15, 2010 |
Fall 2010 |
|
|
Inch Park Pool |
- Complete demolition of the existing outdoor pool
- Construction of new pool complete with barrier free change rooms and administration space
- Beach entry pool with children's water play area, sun shade shelter, on deck seating, accessibility ramps, staff change area.
|
March 31, 2010 |
Summer 2011 |
Walker Outdoor Pool |
| Coronation Pool |
-
A new, fully accessible outdoor pool and pool change house will be constructed on the site of the existing Coronation outdoor pool.
-
The new heated pool will feature water spray features, sun shelters and beach entry.
-
The new change house will also have male, female and family/universal washroom facilities. |
July 2010 |
Summer 2011 |
Victoria Park Outdoor Pool |
| Coronation Arena |
- replacement to the refrigeration and lighting systems
- reconstruct the parking area
- replace the existing wooden seating
- renovate the washroom facilities
- reconfigure the mechanical room
- rehabilitate/replace aging indoor and outdoor fittings/brickwork
|
July 2010 |
Winter 2011 |
|
| Westmount Recreation Centre |
- Construction and expansion of a new community centre
|
New Facility |
TBD |
|
| Lower Stoney Creek Recreation Centre |
- Re-development and expansion of a new community centre
|
New Facility |
TBD |
|
| Morgan Firestone Arena |
- Construction of a second ice surface which meets accessibility standards
- Six new change rooms and referee rooms
- Expanded spectator seating
|
|
|
|
| North Wentworth Arena |
- Construction of a new Twin Pad Area with two NHL standard ice surfaces which meet accessibility standards
- Six change rooms per arena and expanded spectator seating
|
New Facility |
TBD |
|
More information:
Contact:
|