Red Hill Industrial Business Park South TMP Addendum

The City of Hamilton has completed a Master Plan Addendum for the North Glanbrook Industrial Business Park Transportation Master Plan (2006). The North Glanbrook Industrial Business Park or NGIBP is now referred to as the Red Hill Industrial Business Park or RHIBP.

Why? The update was required to address changes to transportation assumptions and requirements since the original 2006 TMP.

Addendum To Glover Road Preferred Alternative

The Glover Road Preferred Alternative recommended in the RHIBP TMP Addendum report was changed by City Council on September 11, 2013. The revised design to Glover Road is:

TMP Addendum
Glover Road traffic island (Schedule A+)

Revision to TMP Addendum
(City of Hamilton Council Resolution, Sept 11, 2013)

Installation of a cul-de-sac between the southern most property of Maple Leaf Foods by 580 GIover Road (Schedule A+)


Study status: Completed November 2013

Classification: TMP Addendum will fullfill the Phases 1 and 2 Class EA requirements of any Schedule B project that are identified and outline additional work that will be required to implement any Schedule C projects that are identified as part of the study. 

Study Area of the Red Hill Industrial Business Park

Related EAs:

Public Information Centre No. 2
Held December 2, 2012
Presented the evaluation of the alternatives for Glover Road. Display panels (PDF, 3.5 MB)

Public Information Centre No. 1
Held June 25, 2012
Introduced the review of the TMP. Display panels (PDF, 5.4 MB)