Prior to commencement of construction | Your building permit has been issued, and you are ready to commence construction of your project. |
Prior to pouring footings | Footings, column pads, slabs are formed, prior to pouring concrete. |
Prior to backfilling foundation excavations | Drainage layer, weeping tile, and stone installed, prior to backfilling. |
Building Sewer and Water installation, prior to backfill | Required drainage storm and sanitary sewer lines installed, proper slope/fall, required cleanouts installed, prior to backfilling. |
Building Drains | All underground plumbing, sewage systems, and backwater protection are installed and ready for text, and prior to backfill. |
Radon Rough-in | The sub-soil pipes, and rough-in of depressurization systems have been installed, and prior to placement of concrete floor. |
HVAC Rough in | Completion of HVAC rough in, supply, return air and plenums. |
Plumbing Rough in | Completion of above ground plumbing rough in, required to air/water test system. |
Framing | Completion of framing, HVAC rough in, and plumbing rough in, prior to installing insulation & vapour barrier. |
Insulation, Vapour Barrier & Air Barrier | Installation of insulation, vapour barrier and air barrier system, prior to installing interior finishes including drywall. |
Fire Stopping of Penetrations through Fire Separations | Completion of fire stopping, and smoke seals for penetrations through required fire separations. |
Fire Separations | Installation of sound insulation, completion of one side of fire separation/shaft wall system, completion of fire separation or fire wall. |
When applicable, commencement of construction or installation of masonry fireplaces & chimneys, factory built fireplaces using solid fuel and chimneys or solid fuel burning appliances (wood stoves) and chimneys | Prior to installation and after completion. |
Installation of Sewage Systems | Prior to backfilling with required fill, bed pipes installed. |
Sewage System Drainage Bed Pipe Layout | Prior to backfilling. |
Sewage System Tank Installation | Prior to backfilling. |
Life Safety Components | Completion & Verification of the fire alarm systems, sprinkler systems, standpipe and emergency lighting systems. |
Grading Inspection | The final grading has been completed, including all hardscaping, seed/sod, swales or other landscaping features. |
Occupancy* | Contact your building inspector to clarify which occupancy requirements apply to your project. |
Final – Completion of the Building Permit** | Completion of work under the approved building permit and OBC requirements. |